SWSOLAR Getting Ready to Break its 2019's & All Time High

SWSOLAR

.................................................................................................................
.................................................................................................................
.................................................................................................................

| KEY HIGHLIGHTS FOR 1Q FY25
...............................................................................

• Unexecuted order value at ~INR 9,396 crore as of June 2024
compared to ~INR 8,084 crore as of Mar 2024
• Company has received new orders / LOI in three domestic
projects worth ~INR 1,016 crore during the quarter
• Company received two turnkey international orders from South
Africa amounting to ~USD 140 mn
• Commenced a pilot project for Solar plus BESS for Reliance

Industries at Jamnagar, Gujarat

• P&L of the company continues to improve
• Consol revenues up ~78% YoY in 1QFY25
• Gross margins at ~11%
• Second consecutive quarter of positive EBITDA, PBT and PAT
at a consolidated level

............................................................................................................
• The company’s balance sheet continues to de-leverage
............................................................................................................
• Total net debt of ~INR 97 crore as of Jun 2024, compared
to net debt of ~INR 116 crore in Mar 2024
• No upcoming debt repayments till 3QFY25



.................................................................................................................
.................................................................................................................
.................................................................................................................


Received order of 900 MW DC in 1QFY25
• Received a turnkey solar PV order from AMEA Power in South
Africa for a ~140 MW DC project
• Through this project, SWREL has achieved a key breakthrough in
the rapidly growing South African solar market.
• We have successfully executed a 90 MW DC order in South
Africa in 2016 previously, and continue to maintain O&M
operations there
• Bagged our second international order from South Africa with a
turnkey package for a 80 MW AC project from Energy Group



.................................................................................................................
.................................................................................................................
.................................................................................................................


alltimehighbreakoutBeyond Technical AnalysisbreakoutzoneFundamental AnalysisinvestinglongterminvestingmultibaggermultibaggerstocksmultitimeframeanalysispositiontradingswingtradingTrend Analysis